The Obama Presidential Center has entered billion-dollar territory, with the foundation overseeing the Chicago campus projecting construction costs of approximately $1 billion. The figure is nearly triple the upper end of the original estimate for the long-delayed [1] project.
The campus was originally expected to open in 2021, with construction estimated at $300 million to $350 million. Federal reviews, legal challenges, and construction delays preceded its eventual opening in June 2026, five years behind schedule.
By the time the center opened, projected costs had already climbed to approximately $850 million. The latest estimate adds another expensive chapter to a project promoted as a historic community investment and tribute to former President Barack Obama.
Emily Bittner, the Obama Foundation’s vice president of communications, confirmed the new projection to Fox News Digital.
“While we continue to reconcile costs and plan ahead for additional capital improvements, we anticipate our total cost for constructing the campus is approximately $1 billion — again, all raised in private contributions,” Bittner said. “This includes investments in additional public art, insurance, scope changes in our Home Court, project management and exhibit installation, among other categories.”
Approximately $909 million in construction-related costs had been recorded by the end of 2025, according to newly released audited financial statements. The project was about 80% complete at that point.
The foundation’s disclosures cover its entire operation, including leadership, education, and community programs in the United States and around the world. Donations and grants fell to approximately $151 million in 2025 from $195 million in 2024.
Fundraising has moved sharply in recent years. It dropped from $311 million in 2022 to $129 million in 2023, rebounded in 2024 and then declined again in 2025.
Total liabilities reached approximately $103.5 million in 2025, compared with $35 million in 2024 and $20 million in 2022. Outstanding borrowing also rose from $15 million at the end of 2025 to approximately $63.5 million by July 2026.
The nonprofit said the borrowed money covered short-term expenses during the final stages of construction. It also said the loans were not secured against its rights to the property.
Money and investments available for everyday expenses fell from approximately $265 million in 2024 to $101 million in 2025. Still, Brian Mittendorf, a nonprofit accounting professor at The Ohio State University, said the organization remained on solid financial footing with more than $1.1 billion in net assets at the end of 2025.
“In terms of the organization’s overall financial health, again, I would say financial health looks quite good,” Mittendorf said. “They have a decent amount of cash, investments, liquidity, and so on. So it’s not like they’re in financial difficulty by any means.”
Mittendorf cautioned that much of the foundation’s wealth is tied up in the center rather than assets that can readily become cash. He also said raising money for insurance, utilities and upkeep could prove harder than raising money for construction.
WATCH:
The 19.3-acre campus occupies historic public parkland in Jackson Park under a 99-year agreement with Chicago. The city received a one-time payment of $10, and the land and buildings are legally owned by the city.
Critics have questioned the foundation’s failure to fully fund a proposed $470 million endowment intended to support upkeep and reduce the risk that taxpayers could eventually face costs. The foundation’s overall endowment reached approximately $14.2 million by the end of 2025, though the amount specifically reserved for the center remains unclear.
The foundation said its city agreement required it to establish an endowment, not fully fund one, before taking control of the site. Officials said construction and leadership programs received fundraising priority, with significant investments in the fund planned for coming years.
Payment disputes remain another cloud over the lavish campus. Several subcontractors have claimed major losses, including businesses the project was intended to support.
Mike Owen, owner of Adamson Plumbing, said his company suffered nearly $4 million in losses, suspended operations, and laid off 25 union workers. The company filed a $1.72 million mechanics lien, and Owen said he still has not recovered the money sought.
The center includes a museum inside a 225-foot-tall, eight-story tower, a Chicago Public Library branch, gardens, an auditorium, meeting spaces and more than 20 commissioned art installations. Home Court adds a 60,000 square foot athletic and community facility.
Unlike traditional presidential libraries, the center does not hold Obama’s original presidential records. Those records are stored at the National Archives in College Park, Maryland, while the Chicago museum displays digital versions and artifacts.