WHAT YOU NEED TO KNOW
  • Two Navy F-35C fighters completed the aircraft’s first launch and recovery testing aboard the future USS John F. Kennedy.
  • The 11 day test period included 34 flights, 122 catapult launches and 122 arrested landings.
  • The trials evaluated F-35C operations with the Ford class carrier’s EMALS launch system and Advanced Arresting Gear.
  • Kennedy was about 99% complete at preliminary acceptance, with formal delivery planned for spring 2027.

Two Navy F-35C Lightning II fighters have completed the aircraft’s first launch and recovery testing aboard the future USS John F. Kennedy, according to Lockheed Martin. Kennedy is the Navy’s second Gerald R. Ford class aircraft carrier.

The 11 days of testing began Oct. 13, the Navy’s 251st birthday. During the trials, the two fighters completed 34 flights, 122 catapult launches and 122 arrested landings.

Both aircraft belong to Air Test and Evaluation Squadron 23, also known as VX-23 and the “Salty Dogs.” The squadron is based at Naval Air Station Patuxent River, Maryland.

The flights formed part of Kennedy’s Aircraft Compatibility Testing. According to the Navy, that process evaluates how the carrier’s launch and recovery equipment works with Navy aircraft.

Trump's Sovereign Wealth Fund: What Could It Mean For Your Money?

Navy photo captions show that the first arrested landing occurred Oct. 13. The first catapult launch followed Oct. 14, putting both major portions of the test program into action during the opening days.

Ford class carriers use the Electromagnetic Aircraft Launch System, known as EMALS, and Advanced Arresting Gear, known as AAG. Nimitz class carriers instead launch and recover aircraft using steam catapults and hydraulic arresting gear.

Lockheed Martin said EMALS provides smoother launches with more precise control. The company also said AAG is capable of handling a broader range of recovery conditions.

Kennedy’s layout presents additional differences from the older Nimitz class. The Ford class has a smaller island, which houses the bridge and flight control, positioned about 140 feet farther back than on Nimitz class carriers.

FREE Gun Law Map: Laws Don't Pause During Social Unrest

Should Election Day be a federal holiday?

By completing the poll, you agree to receive emails from Objectivist.co, occasional offers from our partners and that you've read and agree to our privacy policy and legal statement.

Lockheed Martin said the smaller island and redesigned flight deck alter airflow, exhaust patterns and deck operations. Those differences made the compatibility testing an important step for integrating the F-35C with the newer carrier design.

The sea trials followed shore based testing conducted from January 2024 through May 2025, according to the company. That earlier work validated the fighter’s structural models and verified the software and equipment supporting EMALS and AAG.

Data collected through the testing will help develop launch and recovery guidance for crews serving aboard Ford class carriers. The work gives crews information tied directly to operating the F-35C with the newer launch and arresting systems.

“This is a critical event for the F-35C, Kennedy, and the United States Navy,” said Sean Jackson, vice president of Lockheed Martin’s F-35 Development Program. “For the first time, the aircraft has demonstrated launch and recovery operations from a Gerald R. Ford-Class flight deck, advancing the integration of fifth-generation fighter capability with the world’s most advanced carrier technology.”

Jackson also said that after completion of the test phase, “the Navy has now cleared the F-35C for operations across its entire fleet of aircraft carriers.” A Lockheed official said the Navy retains the “final clearance.”

“The ships are cleared to launch and recover F-35s once the launch and recovery bulletins are published,” the Lockheed official told Defense News. “They will not be ready to deploy until fully outfitted with supporting equipment.”

The F-35C first landed aboard an aircraft carrier in November 2014, touching down on USS Nimitz off San Diego. It has since deployed from modified Nimitz class carriers, while USS Gerald R. Ford has not deployed with the fighter.

A Navy spokesman told USNI News in 2019 that both carrier classes were designed to operate F-35Cs, but required changes for the aircraft to be more effective during a full length deployment. Those changes included stronger jet blast deflectors and classified spaces.

Stars and Stripes reported in October that the Navy plans to retrofit USS Gerald R. Ford for F-35C operations. Kennedy received its modifications during construction after the Navy changed the ship’s construction contract in 2020 to meet a legislative requirement that it be capable of deploying with the aircraft.

The Navy took preliminary acceptance of Kennedy on Sept. 29 following acceptance trials in August. Preliminary acceptance lets the crew test and train at sea while the shipbuilder completes remaining work.

At the time, the Navy said Kennedy was about 99% complete. Formal delivery is planned for spring 2027, while the successful F-35C trials mark a major step toward bringing the fighter and the Navy’s newest carrier design together.